Do data centers use a lot of water — and could one near Bartlett or Elgin end up on your water bill? The short version: water-cooled data centers drink like small towns, but many new ones barely sip. The part that affects your bill isn't the water they use — it's who pays for the pipes. Here's what we could actually verify.

The short answer

Yes — if it uses evaporative cooling, a data center can drink as much water as a small town. A medium-sized facility uses around 300,000 gallons a day, roughly what 1,000 households use. The largest hyperscale campuses reach up to 5 million gallons a day.

But your water bill is probably safe — with one caveat. Municipal water utilities almost everywhere run on "growth pays for growth": the big new user pays connection and capacity fees for the infrastructure its demand requires. The real risk is indirect — if a utility undercharges a giant user or builds ahead of demand, the gap eventually lands on ratepayers. That's exactly the fight happening in Columbus, Ohio right now, and it's the question worth asking about any data center proposed near here.

How much water are we actually talking about?

Servers turn nearly all their electricity into heat, and something has to carry that heat away. The cheapest way at scale is evaporative cooling: air passes over wet cooling towers, water evaporates, and the phase change hauls the heat off. It works beautifully — and it consumes fresh water continuously, because evaporated water doesn't come back. That's the key distinction: this water is consumed, not borrowed.

The numbers vary enormously by cooling design, which is why any honest answer starts with "which kind?"

300,000
gallons/day — a medium evaporatively-cooled facility (~1,000 households)
450,000
gallons/day — Google's average data center in 2021 (Google's own disclosure)
5M
gallons/day — the largest hyperscale campuses, per the EESI (a town of 10,000–50,000)

For scale: one of Google's biggest U.S. sites, in Council Bluffs, Iowa, withdrew about 3.9 million gallons a day and consumed roughly 2.8 million of it, per Google's own environmental report. A peer-reviewed analysis found a single megawatt of evaporatively-cooled capacity drinks about 18,000 gallons a day — so a 100-megawatt facility, a common size for new builds, lands around 1.8 million gallons daily.

The counterweight: a facility on air cooling or a closed loop uses almost no water on site — it just pays more for electricity instead. And the newest AI hardware runs so hot it needs liquid cooling, which circulates coolant in sealed loops with near-zero fresh water. The industry's water trajectory is genuinely better than its electricity trajectory. When a developer says "closed-loop cooling," that's a meaningful claim — but it's worth asking them to put the actual gallons-per-day number in writing, because "closed loop" still needs an initial fill and makeup water.

Where your water actually comes from

To judge whether a data center could strain your water supply, you have to know what your supply is. Here's the verified picture for our area:

Bartlett: Lake Michigan. The village's own documents state plainly that "Bartlett's source water, Lake Michigan" — purchased through the DuPage Water Commission, which receives treated lake water from the City of Chicago's Jardine purification plant. Fun history: as recently as 2017, Bartlett bought about 60% of its drinking water from the city of Elgin before completing its switch to the DuPage Water Commission.

Elgin: the Fox River. About 75% of Elgin's raw water comes from the Fox River, with the remaining 25% from deep wells, per the city's own history page. Its Riverside treatment plant can process up to 32 million gallons a day. Notably, Elgin's official history says the decision to return to the Fox River "has continued to help Elgin attract large corporations and developments, many of which would not locate here without an ample water supply." In other words, Elgin has been marketing its water abundance to industry for decades.

One more piece of context: Illinois' Lake Michigan supply is not infinite. A 1967 U.S. Supreme Court decree caps the state's total diversion at about 2.1 billion gallons per day — shared across Chicago and more than 200 suburbs. Every new large user in the region draws from the same court-ordered pie.

Who pays for the pipes?

This is the question that actually reaches your bill. When a giant new water user shows up, somebody has to pay for bigger mains, upgraded pumps, and expanded treatment capacity. The standard answer from utilities is "growth pays for growth":

  • Connection and capacity fees. New large users pay one-time charges scaled to the capacity they need — often calculated per "equivalent dwelling unit." The whole point is that existing customers don't absorb expansion costs.
  • Developer-funded upgrades. Charlotte, North Carolina's water utility — dealing with the same data-center wave — requires each proposed facility to undergo capacity review and hydraulic modeling, and says the developer pays for main extensions, line upgrades, and capacity improvements. Charlotte Water told local media that data centers operating there "have not caused residential water or sewer rates to increase."
  • The peak-demand problem. Here's where it gets honest: a data center's water use swings with the weather — far more on hot days. Columbus, Ohio is currently pushing to bill data centers for peak water use, because its utility has to build infrastructure sized for the worst days while the current fee structure only really captures average consumption. As one city official put it, the question is whether high-volume users "pay their fair share for the amount of investment that is needed to deliver peak water capacity."

The bottom line: the system is designed so you don't pay for a data center's water. Whether the fees fully capture the true cost — especially peak capacity — is the legitimate open question, and it's being litigated in rate cases, not settled.

The water fights already happening in Illinois

You don't have to look far to see this play out. In 2026 alone:

  • Morris — an alderman voted against the Tract 1-gigawatt data center campus citing water usage and the possible need for a new water facility the city might have to help fund.
  • Joliet — residents sued to stop a proposed $20 billion campus, arguing it could draw 100,000–150,000 gallons a day from an aquifer already projected to fall short of peak demand by 2030.
  • Mahomet — after secret talks leaked, the developer's draft capped potable-water fill for its closed-loop cooling at 750,000 gallons per phase, with the rest from reclaimed wastewater — a sign of how seriously the Mahomet aquifer (drinking water for nearly a million people) is being guarded.
  • Barrington Hills, Naperville, Lisle, Belvidere — a $2 billion campus withdrawn, a 145,000-square-foot proposal killed, another paused, and "Project Hawkeye" opposed at a packed council meeting — all with water among the cited concerns.

The pattern: communities aren't debating whether data centers use water. They're debating whose water, how much, and who pays for the infrastructure. Those are exactly the right questions — and they're the ones to ask if a proposal ever lands near Bartlett or Elgin.

For the full picture on data centers and your other utility bill, see our companion piece on whether data centers raise electricity bills, and our guide to data centers near Bartlett for the verified nearby facilities.

What you can actually do

  • Read your village's water quality report. Bartlett publishes an annual Consumer Confidence Report — it lists your water source, what's in it, and how it's treated. It's the most boring useful document your village produces.
  • Watch for the capacity question. If a large development is ever proposed near you, the question to ask at the village board meeting isn't "will it use water?" — it's "what's the peak-day demand, and what capacity fees is the developer paying?"
  • Know your own usage. The average American household uses about 300 gallons a day. A single medium data center matches a thousand of you. That ratio is the context for every local debate.
  • Fix your own leaks first. A running toilet can waste 200+ gallons a day — the unglamorous truth is that household waste is the part of the water bill you fully control.

Water bill FAQ

Do data centers use a lot of water?

Water-cooled ones do. A medium-sized data center with evaporative cooling uses around 300,000 gallons per day — roughly what 1,000 households use — and the largest hyperscale campuses can reach 5 million gallons per day. But many modern facilities use closed-loop or liquid cooling with near-zero on-site water use, so the honest answer depends on the cooling design.

Where does Bartlett IL get its water?

From Lake Michigan. The Village of Bartlett purchases its drinking water through the DuPage Water Commission, which receives treated Lake Michigan water from the City of Chicago's Jardine Water Purification Plant. The village previously bought about 60% of its water from Elgin before switching fully to the DuPage Water Commission.

Where does Elgin IL get its water?

About 75% from the Fox River and 25% from deep wells, according to the City of Elgin. Its Riverside Water Treatment Plant can process up to 32 million gallons per day. The city has said its ample Fox River supply helped it attract large corporations and developments.

Will a data center raise my water bill?

Probably not directly. Municipal water utilities typically operate on a "growth pays for growth" principle: large new users pay connection and capacity fees covering the infrastructure their demand requires. The risk to residential bills is indirect — if a utility undercharges a giant user or builds ahead of demand, the shortfall can eventually land on ratepayers.

Do data centers have to pay for the water infrastructure they need?

In most places, yes — at least in theory. Utilities charge new large users capital connection or capacity fees, and many require the developer to fund project-specific main extensions and upgrades after a capacity review. The live debate, as in Columbus, Ohio, is whether those fees fully capture peak-day demand and variable use.

Is Illinois limiting data center water use?

Not statewide, but water has become a flashpoint. In 2026, residents sued over a proposed Joliet campus that could draw 100,000–150,000 gallons a day from a strained aquifer, Morris officials debated a new water facility for the Tract campus, and proposals in Barrington Hills, Naperville, Lisle, and Belvidere faced community opposition citing water concerns. Illinois' Lake Michigan supply itself is capped by a 1967 U.S. Supreme Court decree at about 2.1 billion gallons per day.