Looking for data centers near Bartlett, IL? Straight answer first: there are no data center facilities in Bartlett itself — but verified colocation options sit about 20–40 minutes away in Elk Grove Village, Wood Dale, Rolling Meadows, Mount Prospect, Aurora, and Chicago. Every facility below was verified against public listings in October 2026. Confirm specs, certifications, and pricing with the provider before signing.
Last updated: October 25, 2026
Major carrier-neutral colocation and interconnection hub on the DuPont Fabros CH1 campus, just outside Chicago near O'Hare. Supports high-density workloads and private suites with diverse fiber entry.
Carrier-neutral colocation and network hub serving the greater Chicago metro, marketed for low-latency access to Chicago's financial exchanges. Fully redundant power and network paths.
High-resiliency colocation and disaster-recovery facility near O'Hare, designed to Tier III standards. Direct fiber to 350 E Cermak and cloud on-ramps to AWS and Azure.
Smaller regional provider offering colocation alongside hosted servers, online backup, and cloud services, with 24×7 monitoring and managed support.
Network-operator data center on Zayo's own fiber backbone, built for high-bandwidth and low-latency workloads with direct access to major U.S. markets.
Edge-focused facility west of Chicago, acquired by US Signal in early 2026 and being expanded for colocation, private cloud, and AI inference workloads.
Four downtown Chicago facilities in the city's densest interconnection buildings — best for deployments that need maximum carrier choice and exchange proximity.
Chicago's northwest suburbs are one of the densest data center corridors in the Midwest — public listings show more than 200 data center locations within 50 miles of the Elk Grove Village area. Investment keeps flowing in: Tract acquired 343 acres in Morris, IL for a planned 1 GW data center campus, with ComEd lined up to power it. The draw is straightforward: abundant ComEd power, dense fiber along the I-88 corridor, low natural-disaster risk, and latency that works for Chicago's financial exchanges.
For a Bartlett business, that means enterprise-grade colocation is a 20-minute drive away — you don't need to rack servers in a closet anymore.
The closest a large data center has come to Bartlett wasn't in Bartlett at all. In 2026, Whiterose Partners LLC, a Dallas developer, sought concept-plan feedback from the Village of South Elgin for a data center at 33W304 Kenyon Road — unincorporated Kane County land at the northwest corner of Kenyon Road and IL Route 25. The site sits directly against Bartlett: South Elgin's planning staff report lists its eastern neighbor as a Village of Bartlett planned-development district. Because the land sits outside any village, building there required South Elgin to annex it first.
Power was the headline issue. According to the Village of South Elgin Planning & Zoning Commission staff report (Case CD 2026-06, July 15, 2026), the developer filed a 48 MW power request with ComEd, and ComEd indicated that the Bartlett substation has sufficient capacity to serve the site, with the transmission-line extension to the site funded by the developer. Data Center Dynamics reported the project at roughly 200,000 sq ft with closed-loop cooling, a design intended to limit water use.
Residents pushed back hard. An opposition petition grew to about 9,475 signatures, according to the petition organizers, and in August 2026 the South Elgin Village Board denied the annexation. South Elgin then approved a 12-month moratorium on new data centers on October 13, 2026; Elgin adopted its own 12-month moratorium on September 9, 2026.
To be clear: no data center exists or is approved in Bartlett itself, and this was never a Bartlett project. It drew Bartlett-area attention because it would have run on the Bartlett substation's capacity right at Bartlett's border. If you're wondering what projects like this do to household bills, see our explainers on whether data centers raise water bills and whether data centers raise electric bills.
No — no data center facility in Bartlett, Illinois itself could be verified as of October 2026. The closest verified colocation facilities are in Elk Grove Village (about 20 minutes), Wood Dale (about 20 minutes), Rolling Meadows (about 20 minutes), Mount Prospect (about 25 minutes), Aurora (about 30 minutes), and Chicago (about 40–45 minutes).
The closest verified options are in Elk Grove Village, about 20 minutes southeast of Bartlett: ColoCrossing's CHI1 facility at 2200 Busse Rd and QuadraNet's data center at 1905 Lunt Ave. Both are carrier-neutral colocation facilities serving the Chicago metro area.
It depends on your workload: SOC 2 and ISO 27001 are the common baselines for enterprise colocation; PCI DSS matters if you handle payment card data; HIPAA-aligned facilities matter for healthcare workloads. Several facilities near Bartlett — including QuadraNet in Elk Grove Village and Element Critical in Wood Dale — carry these certifications. Always confirm current audit status with the provider before signing.
Colocation pricing varies widely by cabinet size, power density, bandwidth, and contract term, so providers quote per deployment rather than publishing flat rates. Get written quotes from two or three facilities, and ask what is included: power, cross-connects, remote hands, and bandwidth are often priced separately.
No. In 2026, Dallas-based Whiterose Partners LLC proposed a roughly 48 MW data center at 33W304 Kenyon Road in unincorporated Kane County, on land directly abutting a Village of Bartlett planned-development district. The project required annexation into South Elgin, and the South Elgin Village Board denied the annexation in August 2026 after an opposition petition grew to about 9,475 signatures. South Elgin then approved a 12-month moratorium on new data centers on October 13, 2026.
According to the Village of South Elgin planning staff report (Case CD 2026-06), the developer requested 48 MW from ComEd, and ComEd indicated the Bartlett substation had sufficient capacity to serve the site, with the transmission-line extension funded by the developer. The annexation was denied in August 2026, so none of that was built — and the proposal was a South Elgin annexation case, never a Bartlett municipal project.